Executive Summary
PROJECT COST ESTIMATE
The estimated cost for the EAA Storage Reservoir selected plan is $912,895,089.
At this time, the cost estimate does not include any real estate, engineering,
design or construction costs for the proposed STA, which will be included as a
planning level cost estimate in the Final PIR. Preliminary estimate for the
proposed STA include an estimated real estate cost of $8,176,000 for the 1,495
acre site already identified and cost estimates for construction ranging from
$57,800,000 to over $150,000,000, based on comparative costs of similar
construction. The breakdown of the estimated cost for the EAA Storage
Reservoir selected plan is shown in
Tables 1 and 2 (2005 price levels).
TABLE 1: SELECTED PLAN TOTAL COSTS
Borrow and Canal $261,957,593
Levee construction $191,732,312
Cutoff Wall $86,086,678
Utility Relocations $323,857
Bridges $5,636,497
NNR Canal Improvements $35,443,519
Miami Canal Improvements $16,682,354
Bolles & Cross Improvements $20,745,203
Pump Stations $122,520,842
Structures $14,714,934
Manatee Gates $5,325,000
Recreation $342,300
Total Construction Cost $761,511,089
Real Estate $80,134,000
S&A $33,750,000
PED $37,500,000
Total Estimated Cost* $912,895,089
*Does not include STA costs.
TABLE 2: AVERAGE ANNUAL COSTS
Interest and Amortization $60,156,678
Operation & Maintenance $2,413,982
Monitoring $350,000
Total Annual Cost $62,920,660