Section 6 The Selected Alternative Plan
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
6-15
6.2 COST ESTIMATE
6.2.1 Initial Costs
The total estimated initial cost for the selected alternative plan is $912,895,089.
This does not include any real estate, engineering, design or construction costs
for the proposed stormwater treatment area, which will be included at a
Planning level cost estimate in the Final PIR. Current rough order of magnitude
costs for the proposed STA include an estimated real estate cost of $8,176,000
and cost estimates for construction ranging from $57,800,000 to in excess of
$150,000,000, based on comparative costs of similar construction. The estimated
cost of the selected alternative plan features, including real estate (lands and
damages), is shown in Table 6-6.
TABLE 6-6: PROJECT COST EAA RESERVOIR ALTERNATIVE 4
Borrow and Canal $261,957,593
Levee construction $191,732,312
Cutoff Wall $86,086,678
Utility Relocations $323,857
Bridges $5,636,497
NNR Canal Improvements $35,443,519
Miami Canal Improvements $16,682,354
Bolles & Cross Improvements $20,745,203
Pump Stations $122,520,842
Structures $14,714,934
Manatee Gates $5,325,000
Recreation $342,300
Total Construction Cost $761,511,089
Real Estate $80,134,000
S&A $33,750,000
PED $37,500,000
Total Estimated Cost* $912,895,089
*Real estate, engineering, design and construction costs for the STA have not been added to this
table as a conceptual design has not been completed. Additional analysis will be conducted prior
to the Final PIR and during the detailed engineering and design phase of the project to
determine the final design, size, costs, and operations of the STA.
6.2.2 Investment Costs
Department of the Army Engineering Regulation (ER) 1105-2-100 requires that
interest during construction (IDC) be computed which represents the
opportunity cost of capital incurred during the construction period. Interest was
computed for construction and pre-construction engineering and design (PED)
costs from the middle of the month in which the expenditures were incurred