Section 5 Formulation of Alternative Plans
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
5-52
on water stages at certain times of the year, and beneficial responses are
anticipated to begin immediately with the operations of the reservoirs. Actual
restoration of colonization numbers in Lake Okeechobee and WCA-3 may take
several nesting seasons.
5.4.4.5 Sequencing and Adaptive Assessment
The CERP consists of 68 major components and six pilot projects. Significant
uncertainty associated with the individual compartments and the
Comprehensive Plan was recognized during the Restudy. There are a large
number of potential combinations of these compartments that may result from
differences in design and operational schedules developed through the PIR
process. Even as planning efforts for the separate projects evolve, there are also
changes in budgets, policies, resource demands, and operation principles. As
such, a fundamental implementation principle for the CERP is to utilize
adaptive assessment and management in order to continually refine and
improve the performance of the CERP. Incremental revisions throughout the
planning and implementation process of the CERP will lead to optimal designs
and operations of projects to improve performance. The order and schedule for
project implementation will also be optimized to achieve the desired ecological
responses. The use of the adaptive assessment policy minimizes the effects of
uncertainty with respect to the effects of CERP projects on the natural system
and other water-related needs of the region related to the design and
implementation of the CERP.
5.4.4.6 Construction Cost Estimates
No statistical analysis of cost risk was performed. Normal design variances are
expected and normal contingency values are used. The risk of cost overruns is
considered to be low.
5.4.4.7 Project Schedule
It is not anticipated that any new tasks will be required that would increase
overall project delivery dates. As such, no negative impacts to project schedules
are anticipated.
5.4.4.8 Land Available and Acquisition Issues
There is some uncertainty associated with the land availability, cost, and time to
acquire the additional lands necessary for the construction, operation, and
maintenance of Alternatives 2 and 3.