Section 8 Plan Implementation
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
8-1
8.0 PLAN IMPLEMENTATION
The conditionally authorized Phase 1 EAA Project has been reevaluated. It has
been determined that to optimize the design, it is no longer necessary to phase
this Project. The three reasons for initially phasing this Project were because it
was believed that:
1. Only a portion of that lands needed for the entire project had been
acquired by the DOI and SFWMD,
2. There was an opportunity to construct a portion of this Project in a
manner that is mutually beneficial for the Comprehensive Plan and the
sponsor’s Everglades Construction Project,
3. The expedited construction of portions of this Project would provide
multiple environmental, water supply, and flood protection benefits.
Because it has been determined that all benefits anticipated for this Project can
be achieved with lands already acquired, there is no longer any need to phase
the implementation.
8.1 DIVISION OF IMPLEMENTATION RESPONSIBILITIES
Responsibilities for implementing the Selected Alternative Plan (Selected Plan)
will be shared by USACE, on behalf of the Federal government, and the non-
Federal sponsor, SFWMD. USACE and SFWMD will cost share equally in the
design of the projects resulting from this plan. SFWMD has acquired the
necessary lands, easements, rights-of-way, relocation, and disposal areas
(collectively referred to as LERRD) and will operate and maintain the completed
Project. Construction contracts to build the projects will be managed by either
USACE or SFWMD to maintain a 50/50 cost. Rules, which determine how
project responsibilities are shared, are established in federal law and related
implementing policies. Section 601 of WRDA 2000 provides in-kind cost sharing
credit to the non-federal sponsor for design, construction and operational and
maintenance and for treatment of credit between projects to maintain a 50/50
cost share. The draft PIR includes recommendations to credit the non-federal
sponsor for work completed under the Acceler8 program in advance of approval
and authorization of the federal project. At this time, it is anticipated that the
Selected Plan will include SFWMD’s Acceler8 project for the EAA Storage
Reservoir (190,000 acre-feet of storage and appurtenant structures and
features).
Detailed design of the Acceler8 project will be accomplished by SFWMD with
coordination and review by USACE under the Acceler8 program. All project
features will be designed in accordance with USACE regulations and standards.
Construction activities for the Acceler8 project will be in accordance with the
Acceler8 program and will be the responsibility of SFWMD. Crediting for work