Section 9 Summary of Coordination and Environmental Compliance
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
9-7
Certification (WQC) will be met by an NPDES permit. The project is in
compliance with this Act.
9.6.3 Coastal Zone Management Act of 1972
The State Clearinghouse provided comments on September 13, 2002, in response
to a scoping letter and indicated probable consistency. A federal consistency
determination in accordance with 15 CFR 930 Subpart C is included in the
Revised Draft PIR/EIS in Annex C. The consistency review, delegated to the
State of Florida, will be performed during the coordination of the draft PIR.
9.6.4 National Environmental Policy Act of 1969
A scoping letter for the EAA Storage Reservoir project was mailed on July 16,
2002 to federal, state, and local agencies; Native American Tribes; private
organizations; and, interested parties to solicit their views, comments, and
information about resources, study objectives, alternatives, and important
features within the Study Area. In addition, the following activities have taken
place to involve the public in the planning process:
Established a website at http://www.evergladesplan.org/ to provide information
and communication paths to the computer-able portion of the population. Two
public workshops on the EAA Storage Reservoir project were held in Spanish
and English at Belle Glade in August 2001 and January 2003. A series of
Project Development Team (PDT) meetings open to attendance and comment by
the public. The first PDT meeting was held on March 13, 2001. All PDT
meetings were held within 50 miles of the project area.
Information developed from NEPA scoping and outreach processes and other
sources were used in project planning to identify problems and opportunities
associated with the EAA Storage Reservoir project. Many of the issues are
related to the conflict between encroaching human development and the natural
environment. Public comments generally supported the projects goals and
objectives, but expressed concern over the length of the project schedule. There
was public skepticism over the cost effectiveness of storage reservoirs over
storing water in Lake Okeechobee or the Water Conservation Areas because of
increased evaporation and seepage from the reservoirs. Suggestions were also
put forth by the public on investigating alternative approaches to restoring
historic flows and flow-ways. Many of the public comments expressed concern
over potential impact on jobs in the EAA.
The draft EIS was noticed in the Federal Register in October 2005 and released
to the public and agency for review and comment. Comments have been
reviewed, incorporated and responded to in preparation of the Revised Draft PIR
/ EIS. The comment and response matrix is included in Annex H.