Foreword
FOREWORD
A note to the reader of this Revised Draft PIR/SEIS
Prior to completion of this Revised Draft Project Implementation Report (PIR)
and Supplemental Environmental Impact Statement (SEIS), the State of Florida
determined that it was urgent to accelerate funding, design, and construction of
critical restoration projects to capture immediate environmental, social, and
economic benefits in the South Florida region. To that end, the State of Florida’s
“Acceler8” program was established, including the Everglades Agricultural Area
Reservoir A-1 project. The South Florida Water Management District (SFWMD)
is the state agency responsible for water resources management in South Florida
and acts as the non-federal sponsor for federal water resources projects,
including the Comprehensive Everglades Restoration Plan (CERP). The
SFWMD is also responsible for implementing the Acceler8 program.
Since the SFWMD anticipated that the review of this Draft PIR/SEIS under the
CERP Programmatic Regulations, Corps of Engineers policy requirements, and
public and agency review requirements of NEPA, followed by subsequent
preparation and submittal of a Final PIR/SEIS for eventual Congressional
review and authorization were not likely to be completed on the construction
schedule originally established by the SFWMD for the Everglades Agricultural
Area Reservoir A-1 project, the SFWMD decided to pursue a Corps of Engineers
regulatory permit issued under Section 404 of the Federal Clean Water Act
(supported by a separate regulatory EIS) for the Acceler8 project so that
construction could begin as scheduled in 2006.
The Acceler8 project (Everglades Agricultural Area Reservoir A-1 project) is
similar to a component of the NEPA preferred alternative or Tentatively
Selected Plan, described in this Revised Draft PIR/SEIS. The SFWMD’s
proposed Acceler8 project represents approximately one-half the dimensions
(e.g., area and storage volume) of the PIR preferred alternative. The purposes of
the preferred alternative identified in this Draft PIR and the Acceler8 project are
consistent, but the completion of the Regulatory EIS and receipt of associated
permits and required land use approvals are expected to occur more quickly than
a final agency decision on this PIR/SEIS, thereby enabling the SFWMD to
initiate construction in 2006 as scheduled.
The Draft Regulatory EIS is available for public and agency review at the same
time as this Revised Draft PIR/SEIS for the proposed Federal project. For
details of the Acceler8 project, the reader is referred to the Regulatory EIS. The
availability of both documents will be noticed in the Federal Register and the
Regulatory SEIS will be posted on the Jacksonville Corps District web site
(http://www.saj.usace.army.mil/) and this Revised Draft PIR/SEIS is posted on
the CERP website (
http://www.evergladesplan.org).
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006